First witness statement of Mr. LEUNG Ping Kay

Summary

The "1st Witness Statement of Mr. LEUNG Ping Kay" is a formal document detailing Mr. Leung's involvement as a director of China Status Development and Engineering Company Limited in a project for Prestige Constructions & Engineering Co., Limited (PC&E). It outlines the preparation and submission of fire service installation Shutdown Notices (SDNs) to the Fire Services Department for renovation work at Wang Fuk Court. The statement includes details of the contractual agreement, communication methods (primarily through a WhatsApp group), and the specific services provided, such as procurement of fire extinguishers, SDN submissions, and issuance of Form FS251s.

Summary in 繁體中文

本文件為梁炳基先生的第一份英文證人陳述,內容詳述其於王府火災事件中的目擊經過,全文共九頁並附九張圖片,供調查參考。

Key points

  • Mr. Leung Ping Kay is a director of China Status.
  • China Status contracted with PC&E for Wang Fuk Court fire system shutdowns.
  • SDNs submitted to FSD for 8 buildings' FH/HR systems in Wang Fuk Court.
  • WhatsApp group used for project communications between China Status and PC&E.
  • Extensions for FH/HR system shutdowns requested for ongoing tank works.
  • China Status previously worked with PC&E on other renovation projects.

How the Terms of Reference appear in this document

ToR1 Fire safety compliance

Details of submitting Shutdown Notices (SDNs) to the Fire Services Department (FSD) for temporary suspension of fire hydrant/hose reel systems in Wang Fuk Court buildings.

ToR3 Contractual arrangements

Description of the contract between China Status and Prestige Constructions & Engineering Co., Limited (PC&E), including the quotation dated 25th March 2025 and subsequent invoice issuance.

ToR5 Communication and coordination

Establishment of a WhatsApp group on 7th April 2025 for project communications involving Mr. Cheung, Ms. Chung, and Mr. Leung.

In the news

This document connects to these themes in the news coverage analysis (News & Coverage).

Full document (9 pages) — click to expand

Text extraction produced no content (scanned document) — see the extracted images above or the original PDF.

Related documents